Bobcat Bluff 34.5–138 kV Substation — Foundation Material Takeoff

Billings, MT · ECI / EDF · Issued for Construction (CUB Addition) · 30-sheet set · preexisting (unlabeled) foundations excluded

Live foundation takeoff

Foundation quantities.

Review assignments ↓
Total Concrete — Site
–
cubic yards, all new foundations
Rebar — Steel
–
linear feet · A615 Gr60
Rebar — Fiberglass
–
linear feet · GFRP, non-mag
Rebar Weight
–
lbs · from sheet summaries
New Foundations
–
count · piers + slabs
Anchor Bolts
–
all styles combined
A.B. Cage Templates
–
SM1 static-mast cages
Show the math — verify every headline total above

1 · Assign each structure's pier size

The 18 cast-in ("EG") piers share one 1"Ø anchor bolt but come in 4 diameters. Pick each from your foundation location plan. SM1 masts are fixed to the 54"Ø static-mast pier.

Swipe the table to see all columns →

Struct.DescriptionQtyPiers ea. Total piersFoundation typeConcrete CYRebar LF

2 · Concrete & rebar by foundation group

Swipe the table to see all columns →

FoundationSizeCountCY ea.CY total Rebar LF ea.Rebar LF totalRebar wt (lb)Rebar
Weights are the drawings' stated rebar totals (steel). AF3F's GFRP #4 hoop weight is not listed on the sheet, so its number reflects the steel #8 only.
Show rebar detail — every bar + how each linear-foot figure is calculated

Swipe the table to see all columns →

FoundationBarMarkBars ea.LF ea.Lb ea.MaterialHow the LF ea. is figured
Hoops (the #4 ties) are rings: length = π × ring diameter (pier − 6″ for 3″ clearance each side) + a ~1'-3″ lap to close them. Straight bars = count × length. All match the sheets' stated linear feet.

3 · Anchor bolts by style

Cast-in & cage bolts are fully counted from the structure sheets. Post-installed slab bolts (EZ/BZ/AA) depend on slab counts set in section 5.

Swipe the table to see all columns →

StyleDescriptionInstallQty
Show the math — anchor bolts, counted by structure

4 · Templates & miscellaneous

Swipe the table to see all columns →

ItemDescriptionQty

5 · Slab foundations & missing sheets — needs your input

These items are defined in the set but their counts aren't in this PDF (they live on the foundation plan / on sheets not included). Enter counts to include them.

Swipe the table to see all columns →

ItemType / sizeNotesQty

6 · Structure (connection) bolts — reference

Not foundation anchors — these bolt the steel members together. Add 5% overage per sheet note 11 when ordering.

Swipe the table to see all columns →

BoltUsed onQty
Show the math — structure bolt totals